Thames Water's White Horse Reservoir application reached the Planning Inspectorate on 19 November. It decides by 17 December whether to examine it.
Thames Water’s application to build the White Horse Reservoir south west of Abingdon is now with the Planning Inspectorate. The Inspectorate says it received the application on Thursday 19 November.
It will decide by 17 December 2026 whether to accept the application for examination.
Overview
- Received: Thursday 19 November 2026, project reference WA010005.
- Next decision: whether to accept it for examination, by 17 December 2026.
- Comments: none can be made yet. Registration opens only if the application is accepted.
- Who decides in the end: the Secretary of State at the Department for Environment, Food and Rural Affairs, not the district council.
What the application covers
The scheme was previously known as the South East Strategic Reservoir Option, or SESRO. It would sit west of the A34 between Marcham, Drayton, Steventon, East Hanney and Grove.
The Inspectorate’s project page describes a reservoir of more than 30 million cubic metres of water storage. The application also covers the works needed to build and run it, including:
- a water transfer tunnel or pipelines
- inlet and outlet structures and pumping stations
- watercourse diversions and new access roads
- temporary railway sidings for handling materials
- parking, wildlife and environmental areas
- leisure, recreation and education facilities
Thames Water’s September construction plans put 17 construction entrances around the site (our report on the access plans).
What happens before 17 December
At this stage the Inspectorate checks whether the application is complete enough to examine. Nobody can comment on it yet.
If it is accepted, the Inspectorate will publish:
- the acceptance decision
- the representations it received from local councils on the consultation
If it is not accepted, it will publish its reasons and remove any documents already on the project page.
Vale of White Horse District Council said on 12 November that it has “deep concerns” about the reservoir. Cllr Bethia Thomas, the council’s leader, said then: “In about a month’s time we will know if this has been accepted for examination by the Planning Inspectorate.” She said the council expects all of Thames Water’s application documents to be published in early 2027, with public examination hearings later in 2027. We covered the council’s position in full last week.
What it means for you
Nothing can be said for or against the reservoir until the decision on acceptance is made. If it is accepted, residents can register to have their say. The Inspectorate says the registration period is set by Thames Water but must last at least 30 days. Registering is what lets you make representations to the examination, in writing and at the hearings.
The Inspectorate’s project page has a “Get updates” sign-up, which emails you when registration opens. The council keeps its own updates on its NSIPs hub. We will report the acceptance decision when it is published.
Sources
- Planning Inspectorate: White Horse Reservoir (WA010005), project information and project updates, read 20 November 2026.
- Vale of White Horse District Council: Council fights to get best outcome for local people as reservoir application progresses, 12 November 2026.