The A34 Lodge Hill junction north of Abingdon will now be finished in early spring 2027, not before Christmas. Work on the south roundabout runs through December.
The new south-facing slip roads at the A34 Lodge Hill junction will not be finished before Christmas. Oxfordshire County Council now expects the scheme to be complete in early spring 2027.
The council announced the change on 18 November. Work on the junction’s south roundabout will carry on through December, up to the Christmas break.
Overview
- New finish: early spring 2027, instead of before Christmas 2026
- Why: some Lodge Hill work was paused while David Wilson Homes rebuilt the Peachcroft roundabout nearby, because both needed traffic management on the same stretch
- Peachcroft: the developer’s roundabout works are now complete, the council said
- Where it stands: stages one to three are done, stage four is almost done and stage five is about to start
- December: work on the south roundabout continues up to Christmas
Why it slipped
Lodge Hill is the junction where the A4183 Oxford Road meets the A34, between Abingdon and Oxford. It has only ever had slip roads facing north. The council is adding slip roads to and from the south, with two roundabouts linked by one bridge. Its scheme page says the junction will give shorter journey times and enable more than 1,000 new homes in Abingdon by 2031.
In September, the council let its own Lodge Hill work and the developer’s Peachcroft roundabout work run side by side. It said that would be shorter overall. But the two schemes needed traffic management on the same busy stretch of the A4183.
The council said some Lodge Hill work was “temporarily paused to improve traffic flow and safety” while Peachcroft was being upgraded. Now that Peachcroft is finished, the south roundabout work can carry on.
Councillor Liz Leffman, the cabinet member for highways, said: “Unfortunately, the overlap in traffic management requirements for the two schemes means that we will not now be able to achieve the previously hoped-for completion before Christmas.”
She added that the team is “now working towards completion in early spring 2027”.
What is left to build
The council says the first three stages are complete. Stages four and five cover:
- realigning the A34 northbound on slip
- building the central section of the north roundabout
- building the central and western sections of the south roundabout
- tying the new Egertons access road into the south roundabout
- building the A34 southbound on slip
The scheme page says the work also includes traffic calming on local roads and an upgraded southbound layby on the A34 near Harwell. Main construction began in September 2025.
What it means for you
- Through Christmas, expect the works and traffic management at Lodge Hill to stay. The council has not published new dates for any lane or road closures linked to the delay; we list the current closures around Abingdon as they are announced.
- Heading south on the A34, you still cannot join or leave it at Lodge Hill until the new south-facing slips open in the spring.
- Peachcroft roundabout, where Oxford Road meets Dunmore Road and Twelve Acre Drive: the council said on 18 November that the developer’s works there are complete.